GATOR
SLOUGH STORM WATER MODEL
Final
Report
The
purpose of this model report is to evaluate the flood stage implications of a
one- foot increase in the crest elevation of several weirs in the Gator Slough
canal system. The objective of this
crest change is to store more water in the water table and canals during the wet
season for use during the following dry season. The model was constructed using the Storm Water Management
Model developed by XP-Software (XP-SWMM2000).
The
modeling objectives are to run the 5, 25, and 100-year storm events and estimate
the flood stages for these events with and without the crest elevation changes.
The project area is located in Cape Coral City, between Pine Island Road
(S.R. 78) and the northern edge of Lee County.
Canals included in the model are Gator Slough, Shadroe, Horseshoe and
Hermosa. The land area modeled in
detail measures 25 square miles and is bounded by U.S. 41 on the east, Pine
Island Road on the south, Matlacha Pass on the west and the Cape Coral city
limits on the north. The
contributing watershed to the east of U.S. 41 is approximately 33 square miles
of low-density residential and undeveloped lands.
This area was incorporated into the model through historical (USGS) and
stochastically generated flow data sets. These
input hydrographs provide boundary inflow to the modeled watershed of Gator
Slough. The model was calibrated
using a 24-day data set collected between 5th and 28th of
September, 1996. This was
considered to represent a one-year storm event. Another 24-day period (July 12th
to August 4th, 2001) provided the verification data corresponding to
a 25-year event. The
calibrated/verified model was then run for three design events:
(i)
5-year, one-day rainfall event of 5.2 inches
(ii)
25-year, three-day rainfall event of 10.6 inches
(iii)
100-year, three-day rainfall event of 12.91 inches
These
events were simulated first with the target weir crests (Weirs #11, 13, 14, 15,
19) set to their existing conditions. The
model simulations were repeated with the weir crests raised by one foot.
Interconnections between sub basins 6 and 7, sub basins 7 and 9, and sub
basins 9 and 10 were not included in the model since preliminary modeling show
low gradients between the areas. Thus
inclusion of these interconnections would provide little additional model
performance enhancements. Also not
included in the model is a Transfer Pump Station, which conveys water from Basin
9 to Basin 4.
When
compared to data collected by USGS corresponding to a 5-year rainfall event,
model flow volumes were 14% less than measured flow values on Gator Slough.
Only one rainfall station was available to represent the entire 25 square
miles watershed. Agreement was very
good (less than 8% difference) between XP-SWMM predicted peak flow (764 cfs) for
Gator Slough at S.R. 765 and the Gumbel estimates generated from USGS measured
data (826 cfs). Simulated water
surface elevations were approximately 0.1 foot above USGS measured values.
XP-SWMM water surface elevations were less than 0.5 feet below Johnson
Engineering estimates [1]. The
previous Johnson Engineering modeling study was conducted using the HEC-2
program. The Johnson Engineering
model was not subject to calibration using measured data.
Thus, it is not surprising that the new XP-SWMM dynamic routing model
delivers results that show much better agreement with stage and flow data
measured by the USGS.
When
compared to the verification event data collected by USGS (very similar to the
25-year design event), model flow volumes were 17% less than measured data on
Gator Slough. Simulated water
surface elevations were approximately 0.5 feet above measured values.
However when compared to Johnson Engineering modeling results, the
25-year XP-SWMM water surface elevations were 3 feet below Johnson Engineering
estimates, derived from the HEC-2 model. Agreement
was very good (less than 1.5% difference) between XP-SWMM predicted peak flow
(1300 cfs) for Gator Slough at S.R. 765 and the Gumbel estimates generated from
USGS measured data (1281 cfs)
When
the model was extended to the 100-year event, XP-SWMM simulation generated water
surface elevations 3 feet below Johnson Engineering’s estimates.
When the target weir crests were raised, the 100-year XP-SWMM model
generated water surface profiles that increase from a minimum of 0.0 feet
(almost no change) at U.S. 41 to a maximum of 0.6 feet at Weir #11.
However these increased water surface elevations were still below the
pre-modification Johnson Engineering HEC-2 model results.
Agreement was very good (less than 2.2% difference) between XP-SWMM
predicted peak flow (1692 cfs) for Gator Slough at S.R. 765 and the Gumbel
estimates generated from USGS measured data (1656 cfs).
Based
upon results of the new XP-SWMM simulation of the Cape Coral canal system, very
little additional flooding is expected to result from raising the target weirs.
Furthermore, all design event flood stages associated with the raised
weir conditions are still well below the previously predicted values.
Therefore, if prior Johnson Engineering HEC-2 model estimated water
surface profiles were deemed acceptable according to flood stage criteria, then
the post-modification water surfaces as predicted by XP-SWMM should also be
acceptable. The reliability of
these XP-SWMM results is supported by favorable comparisons with USGS
measurements. In fact XP-SWMM
results are still conservative relative to City of Cape Coral measured stage
data for a 25-year event documented in July 2001.
The XP-SWMM predicted water surface elevations for this event were
approximately 3 feet above measured stages over the middle and upper reaches of
Gator Slough.
Results
of the XP-SWMM model implementation on the Gator Slough, Horseshoe, Hermosa and
Shadroe canals of Cape Coral show very little additional flooding due to
increasing weir crest elevations by 1 foot at Weirs 11, 13, 14, 15 and 19.
For the 100-year design simulations, water surface profiles increased by
a maximum of 0.6 foot in a limited reach of Gator Slough between Burnt Store
Road (S.R. 765) and Chiquita Boulevard. Horseshoe
canal showed a slightly greater stage increase (0.8 foot) along the lower reach
between Burnt Store Road and Chiquita Boulevard. Hermosa and Shadroe canals showed little change for flooding
in their downstream reaches between Burnt Store Road and Chiquita Boulevard.
The
modeling results presented in this report show a worst-case scenario.
These conditions should not actually occur assuming the Operating
Protocol Table procedures are followed, as developed and presented in the City
of Cape Coral project permit application document.
This table provides conditions for the City to add or remove 1-foot stop
logs in response to monitored water levels in the canals.